Retrofit First: Higher Returns & Lower Carbon

Sustainability and financial performance aligned
Most CFOs still assume sustainability costs more. Oxford Terrace, Christchurch shows the opposite.

After severe earthquake damage, the owner faced two options:

OPTION A — DEMOLISH & REBUILD (modelled scenario)

  • NZD 15M capex

  • 32-month timeline

  • 1,046 tCO₂e upfront embodied carbon

OPTION B — STRENGTHEN & RETROFIT (Post-Tensioned rocking)

  • NZD 9M capex

  • 27-month timeline

  • 203 tCO₂e upfront embodied carbon

They chose retrofit.

———

THE RESULTS

Based on a like-for-like rebuild benchmark using verified material CO₂ data:

  • 81% reduction in upfront embodied carbon (~843 tCO₂e avoided)

  • 5 months earlier return to market

  • 30% higher Net Present Value

  • IRR increased from 12.4% to 18.1%

  • Seismic upgrade from 34% to >100% NBS

  • +74% average apartment sale uplift vs rating valuations

This was not philanthropy.
It was capital efficiency.

———

WHAT MADE IT POSSIBLE?

  • Controlled rocking interface at the base

  • 37m-long vertical post-tensioned tendons

  • Superstructure tied from top to base

  • Energy dissipation with re-centering capability

Resilience restored.
Material mass preserved.
Demolition avoided.

———

THE BIGGER PICTURE

Choosing retrofit over rebuild delivered:

✔ Lower capital outlay
✔ Lower carbon
✔ Faster cash flow
✔ Higher investment returns
✔ Award-winning engineering

Retrofit-first is not a compromise. It is a strategy.

If faced with the choice, would you retrofit or rebuild?

In partnership with Terrascope and engineered by BBR VT International & Contech Engineered Solutions NZ this is a proof that climate action and financial performance can align.

Recognized at the Structural Awards 2024


BBR VT International Ltd
Ringstrasse 2
8603 Schwerzenbach
Switzerland
T +41 44 806 8060

www.bbrnetwork.com

LinkedIn YouTube
Previous
Previous

Proceq to Open New GPR Excellence Training Centre in Málaga, Spain

Next
Next

Stahlton AG Office Relocation of Zurich office from Hinwil to Schwerzenbach